Marseille just 10x'ed its power capacity. Is this the Infrastructure leap of the decade?

By Staff Report · 2 min
Marseille just 10x'ed its power capacity. Is this the Infrastructure leap of the decade?

The Port of Marseille Fos has effectively ended the "pilot phase" of maritime electrification. With a February 2026 update to the CENAQ (Connexion Electrique des Navires à Quai) project, the port has tripled its capacity target to 150 MW by 2028. This represents a 1,000% increase from its 2016 baseline, positioning Marseille not just as a transport node, but as the primary high-voltage energy hub of the Western Mediterranean.


Scalability Through Technical Partnerships


The massive jump to 150 MW is a direct response to the Med-ECA (Emission Control Area) requirements and the tightening FuelEU Maritime standards. To meet this demand, the port is moving away from bespoke, slow-build installations toward standardised, high-performance solutions.

This is where industry suppliers like ShoreLink come into play. As a key provider in the shore power space, ShoreLink’s technology; specifically their CruiseLink and mobile cable management systems addresses the primary physical bottleneck of port electrification: the connection interface.


  1. High-Frequency Capability: ShoreLink’s recent updates highlight their focus on the "CruiseLink" architecture, which allows for rapid, safe, and high-capacity power transfers. This is essential for Marseille’s Léon Gourret cruise terminal, where multi-vessel, 32 MW simultaneous connections are now the standard.
  2. Modular Flexibility: A core part of the Marseille strategy is the ability to service diverse fleets. ShoreLink’s mobile and telescopic cable management systems ensure that the port can service everything from international ferries to ultra-large cruise ships without expensive, permanent quay modifications for every berth.
  3. Synchronization & Safety: ShoreLink’s systems facilitate the critical "blackout-free" transition. By integrating advanced control systems, vessels can switch from auxiliary engines to the 150 MW Marseille grid with zero disruption to onboard operations.


Marseille is no longer just "trying" shore power; they are building a utility-scale infrastructure. The partnership with ShoreLink is the key to their success because it addresses the operational reality of a busy port. If you can’t connect a ship quickly and safely, the 150 MW on the grid is wasted. Marseille’s choice to use standardised, mobile connection hardware ensures they can maximize their massive investment from day one.


The Marseille 150 MW Expansion: Key Data


  • 🏗️ Total Project Name: CENAQ (Connexion Electrique des Navires à Quai)
  • ⚡ Power Capacity: Scaled to 150 MW by 2028 (A 1,000% increase since 2016)
  • 💰 Total Investment: €169 Million (€81M already spent + €88M committed)
  • 🛠️ Key Tech Partner: ShoreLink (Specialising in the CruiseLink & CMS interface)
  • 🔌 Connection Type: High-Voltage (11,000V) with 50/60 Hz frequency conversion
  • 🛳️ Berth Capability: Simultaneous 32 MW supply at the Léon Gourret cruise terminal
  • ☀️ Energy Mix: 18 MWp of solar power integrated directly into the port’s smart grid
  • 📉 Environmental ROI: Targeted reduction of 47% CO2 and 80% SOx emissions
  • ⏱️ Efficiency Gain: ShoreLink mobile arms reduce "time-to-plug" to under 15 minutes