Cold ironing in the Mediterranean: which ports can plug in a ship today
the future.
The Mediterranean holds more than a third of the shore power projects on DTF's map. Ships can use very few of them.
DTF checked all 49 Mediterranean ports on its shore power map against port authority, operator and supplier records. A ship can plug in and draw power in commercial service at eight of them today. Italy has the most projects in the region, 23, and none of them yet offers cold ironing as a commercial service.
Where a ship can plug in today
| Port | Country | Terminal and ships | In service since |
|---|---|---|---|
| Marseille Fos | France | Ferry quays (Corsica and Maghreb ferries); Cruise Terminal 1, three ships at once | Ferries January 2017; cruise 11 April 2026 |
| Valletta, Grand Harbour | Malta | Cruise: Pinto Wharf, Deep Water Quay, Boiler Wharf, up to five ships at once | 1 December 2023 |
| Barcelona | Spain | Hutchison BEST container terminal, 8 MW for two ships (pilot phase); Grimaldi ferry terminal, Barcelona to Palma route | Container 17 September 2024; ferry 31 March 2025 |
| Palma | Spain | Moll de Paraires ferry berth, 1.6 MW | May 2024 |
| Sète | France | Ferry quays, four connection points, 6.3 MW | 20 May 2025 |
| Toulon | France | Ferry terminal, three ferries or one cruise ship | 2025 (accepted June 2025) |
| Alcúdia | Spain | Ferry terminal, fast ferry, low voltage | 30 July 2026 |
| Asyaport, Tekirdağ | Türkiye | Container terminal | October 2024 |
Three of the eight take cruise ships: Valletta, Marseille and Toulon. Valletta connected its first ship, Viking Saturn, on 1 December 2023 and recorded 94 connected calls and about 3.7 GWh of electricity supplied in its first year, according to Infrastructure Malta. Marseille opened cruise connections at its first terminal on 11 April 2026 with MSC World Europa, Costa Toscana and Costa Fascinosa connected at the same time. Barcelona's cruise terminals are not yet connected. Shore power for the MSC terminal is due in 2027 and Terminal G was awarded in April 2026, both fed from a new port substation under the Nexigen electrification plan.
Use varies. Toulon had connected 22 port calls by October 2025. Alcúdia and Asyaport have each reported a first connection, not yet a pattern of regular use. Alicante finished shore power works at four cargo berths in September 2023, but DTF found no record of a ship connecting, so it is not counted here.